Free tool
Conduit Run Planner
Answer 4 quick questions about EMT, rigid steel, IMC or PVC conduit. Find out what size you need, whether you need a pull box, and how wide your bends should be.
What cables are going in the conduit?
What type of conduit?
How long is the conduit run?
How many bends are there?
Here’s what you need
The 4 rules this planner uses
- Don’t overfill: 40% full for three or more cables (30% if you want spare room).
- Keep pulls short: no more than 30 m between pull points.
- Limit the bends: no more than 180° of bends between pull points, for example two 90° corners.
- Bend gently: bend radius at least 6 times the conduit’s inside diameter (10 times for conduit over 50 mm).
If a run breaks the length or bend rule, the planner adds a pull box to split it into shorter, easier pulls. If the conduit it suggests is too big for your wall or ceiling, it also shows how many smaller conduits you can use instead.
Related tool
Want to check one conduit or a cable tray in detail? Use the Conduit & Cable Tray Fill Calculator.
Based on common telecom practice (TIA-569) and BICSI TDMM, Chapter 6, Horizontal Distribution Systems. For planning only; always follow your project specification and local codes.